End-to-end Documentation from Initial Inventory to Final Sign-off
Rosenberger Optical Solutions & Infrastructure (Rosenberger OSI), a European manufacturer of innovative fiber-optic cabling infrastructures, has relocated approximately 500 servers, switches, and other IT components of Helmholtz Munich to a colocation data center. The scope of services covered an inventory, the removal and transport of the hardware, and its reinstallation, recabling, and final inspection. End-to-end documentation formed the basis for the coordinated migration.
Planning and Documentation as the Foundation
When relocating production IT infrastructures, devices, connections, and cabling must remain clearly traceable after the move. At the same time, downtime must be minimized and technical dependencies taken into account. Helmholtz Munich β German Research Center for Environmental Health β commissioned Rosenberger OSI to plan and execute the hardware relocation.
The goal was a smooth transfer with minimal downtime and complete documentation of all systems. At the start of the project, the team recorded the existing infrastructure, documenting cable lengths, ports, cable numbers, and the power supply, among other details. The data was compiled into a central list and continuously updated until the move.
Clear Mapping Down to the Destination Rack
Based on the inventory, the project team compared the installed hardware with the existing data. Using a transport list, it assigned each device to its intended position in the new data center, including the rack and rack unit.
The patch and power cables were then removed, and the devices were taken out of the racks. Lifting equipment was used for heavy hardware as needed. The components were secured on pallets for transport, and the specialty and power cables were packed separately. The equipment was transported in trucks equipped with air-ride and liftgates. Visual inspections during removal, photographic documentation, and an incoming inspection at the new site made the condition of the equipment traceable at every handoff point.
Reinstallation and Recabling
The team installed the hardware at the new site in the specified positions. The fiber-optic and copper patch cabling was restored using new cables. The team coordinated the specific cable routing with the customer on-site. At the same time, it updated the documentation to include the connections between devices, racks, ports, cable types, and cable numbers. Cabling was followed by a final inspection and troubleshooting as needed.
Accounting for Technical and Organizational Risks
Potential disruptions were taken into account as early as the preparation phase. On-site technical support and fallback solutions were planned in case of hardware failures, and immediate technical assistance was available for inaccessible systems.
By the end of the project, approximately 500 IT devices had been installed and cabled in the colocation environment. βWith a move of this scale, success is determined long before the first piece of equipment is moved. We documented every cable, every port, and every target position and kept the documentation up to date right up until moving day. This made it possible to install and connect each system in exactly the right place,β says Stephan Riechmann, Senior Project Manager at Rosenberger OSI.