Use Case | Relocating hardware to a colocation data center

  

Wave-based data center relocation involving approximately 500 hardware components

Customer

Helmholtz Zentrum München – Deutsches Forschungszentrum für Gesundheit und Umwelt (GmbH)

Short description of the project

During the project, it was necessary to relocate some 500 items of IT equipment, including servers and the corresponding switches, to a colocation data center. The aim was to ensure the trouble-free transfer of the hardware, while minimizing downtimes and providing complete documentation for all systems.

  

Services provided by Rosenberger OSI:

The provided services comprised:

  • Project management: Planning, coordination and control of all subcontractors for the entire period of the relocation
  • Documentation: Provision of a complete record of the hardware, cabling and power supply equipment, including updates before, during and after the relocation
  • Disconnection of cabling, removal and packaging of the hardware
  • Transport of the equipment to the new location
  • Removal from the transport packaging, installation and cabling at the destination site, including documentation
  • Troubleshooting and quality control through to final acceptance

A team of up to nine people – consisting of a project manager, four technicians and up to four transport personnel – assisted in the relocation for the entire duration of the project.

  

One key element contributing to the success of our data center relocation was the excellent support we received from Rosenberger OSI. The team’s expertise and hands-on commitment were of incalculable value throughout the entire project. From the painstaking organization of the cables through to the professional coordination on site, the transfer was conducted without a hitch, on schedule and in a carefully controlled way,” explains Dr. Alf Wachsmann, Head of DigIT Infrastructure & Scientific Computing at Helmholtz Zentrum München.

  

Project stages

1. Documentation

  • Complete record of all hardware and cabling components, including cable lengths, ports, cable numbers and power supply
  • Structured entry of all the data in the supplied “Equipment Cabling” list
  • Identification and reporting of non-documented cables or connections with non-identified destinations
  • Ongoing harmonization and continuous updating of the documentation through to the final relocation
  

2. Preparations for relocation

  • Harmonization of the existing documentation with the installed hardware in order to identify and take account of changes
  • Creation of a detailed transport list, including unique identification of all devices and their target locations (rack, height unit)
  • Professional disconnection of all patchcords and power cables by Rosenberger OSI
  • Removal of all equipment - including heavy hardware items using lifting gear - and secure placement on Euro-pallets
  • Packaging of special cables and power cables in polycarbonate (PC) tub trolleys ready for transport
  

3. Transport

  • Loading of all systems onto trucks with air cushioning and lifting platform
  • Professional load securing in accordance with applicable transport and safety guidelines
  

4. Installation at the destination

  • Professional unloading and secure transport to the target cage
  • Assembly of the rack rails and precise installation of the hardware in accordance with the customer’s specifications
  
  • Reconnection of the fiber-optic and copper patch cabling using new cables
  • Conduct of a final check, troubleshooting and end-to-end documentation of the cabling in accordance with the “Device Cabling” list
  
  • Powering-up of the hardware following consultation with the responsible personnel
  • Professional disposal of the transport packaging
  

Safe Implementation and Quality Assurance

Agreement with the customer

  • Joint on-site agreement on the routing of the cables inside the racks
  • Use of the agreed cabling for all components

Protective measures

  • Secure packaging of the hardware with stretch film and loading on Euro-pallets
  • Storage of rack rails and power and special cables in PVC tubs

Quality control

  • Visual inspection of the equipment on removal
  • Photographic documentation during transport
  • Check for completeness and possible transport damage at the destination
  • Final check and approval by the IT contact person at Helmholtz Zentrum München

Challenges and measures taken

  • Failure of power supply units or hard disks: On-site troubleshooting and implementation of a possible fallback solution
  • System accessibility at the new site: Technical support directly on-site
  • Changes to deadlines: Alternative deadline in the event of unforeseen events or staff absences due to illness
  • Missing permissions or access credentials at the destination site: Prior agreement and careful planning
  • Failure of lifts in the data centers: Planning of alternative transport routes 

Related articles

Success Stories

Data highway connection for central Germany

Data highway connection for central Germany. Rosenberger OSI is supporting envia TEL during the expansion of DE-CIX Leipzig

Learn more
Success Stories

Modernization and optimization of optical fiber infrastructure

Rosenberger OSI and Modul’Data Center have been supporting NAVER LABS Europe

Learn more
Success Stories

Future-oriented cabling secures the supply network at TenneT

TenneT relies on modern control centers to monitor its grids, that can grow with the requirements of the dynamic energy market.

Learn more
Blog & Vlog

Interview with Samuel Premkumar: Part 1

Talent shortages, infrastructure bottlenecks, and soaring demands are creating pressure points for the data center industry. Samuel Premkumar from Rosenberger OSI is exploring solutions.

Learn more