Successful implementation of AI infrastructure projects in Europe
Services provided
Point-to-point installation of 2,500 to 10,200 AOC cables between core switches, access switches and server racks
Short description of project
Rapid installation of AI infrastructure clusters in hyperscale data centres in less than ten days.
Another five days were used uninterruptedly for validation of the installed cables and connections, including error checking.
A total of seven installation projects were carried out at various European locations: 2x Paris, Warsaw, Milan, Madrid, Bergamo and Zurich.
A team of two technicians and one project manager worked continuously on-site on each of the projects – from final verification through to acceptance by the customer.
Communication with the customer / reporting
The customer was kept informed of the progress of the project through daily on-site or remote meetings. The progress report was based on a prespecified form provided by the customer and contained information about the defined key indicators, e.g. the quantities of cable laid, pulled, connected and installed.